Key Takeaways:

  • The US offshore wind sector faces a genuine existential challenge in 2026 as federal permitting reversals under the new administration threaten projects representing over 15 GW of planned capacity, with the Inflation Reduction Act’s Investment Tax Credit provisions under political pressure.
  • State-level offtake agreements in New York, Massachusetts, New Jersey, and Connecticut remain the commercial foundation for US offshore wind, but developers including Ørsted, Equinor, and BP are renegotiating contract terms or withdrawing from projects where economics have deteriorated.
  • The Jones Act vessel constraint remains the most immediate technical bottleneck — with only Dominion Energy’s Charybdis as a US-built WTIV currently operational, the installation infrastructure gap threatens to delay projects well into the late 2020s regardless of permitting outcomes.

The Federal Reversal: What Has Actually Happened

The political landscape for US offshore wind changed dramatically following the 2024 Presidential election. The Trump administration moved quickly to pause new federal offshore wind leasing, suspend permitting reviews for projects in the federal pipeline, and direct the Bureau of Ocean Energy Management (BOEM) to undertake a comprehensive review of the offshore wind programme. Executive orders signed in January and February 2025 effectively halted most federal action on offshore wind leases and associated transmission permits on the Outer Continental Shelf.

The legal and commercial consequences have been significant. Projects with approved construction and operations plans (COPs) — the federal permit that authorises offshore construction — but not yet under construction are caught in a permitting limbo. BOEM has been instructed not to issue further federal approvals, and existing permit holders face uncertainty about whether their approvals remain valid or could be challenged administratively.

The projects most directly affected include several in advanced stages of development: New England Wind (previously Vineyard Wind 1), Sunrise Wind, Revolution Wind, and several Equinor/BP Empire Wind phases. Vineyard Wind 1 — the first commercial-scale offshore wind project in the US, which began offshore construction in 2023 — has encountered additional complications around its turbine supply chain (Siemens Gamesa blade manufacturing issues at its Gijón facility) as well as the federal policy environment. Construction continues onshore and on specific permitted scopes, but the project’s timeline has extended significantly from original plans.

The ITC: The Financial Architecture at Risk

The Inflation Reduction Act’s offshore wind provisions — particularly the 30% Investment Tax Credit (ITC) extended to offshore wind projects commencing construction before the end of 2025, with additional adders for domestic content — were the commercial foundation upon which the second generation of US offshore wind projects was financially modelled. Remove the ITC, and the economics of most US offshore wind projects, already strained by cost inflation, become unviable without significant PPA price increases.

Congressional discussions around the IRA’s renewable energy provisions have introduced uncertainty into project planning. While full repeal of the ITC is considered politically difficult given the economic benefits flowing to Republican-held states through manufacturing investments, modifications — reducing the ITC percentage, tightening the domestic content requirements, or advancing the phase-out timeline — are active policy discussions. Developers are modelling scenarios with ITC at 15–20% rather than 30%, and in those scenarios, several projects that were marginally economic at 30% ITC become clearly unviable.

The financing community — infrastructure funds, commercial banks, and tax equity investors who are the primary capital providers for US offshore wind — is taking a cautious stance. Tax equity investors particularly are wary of committing capital to projects whose ITC benefit may be retrospectively altered or subject to legal challenge. Without tax equity, the project finance structures that underpin US offshore wind development unravel.

State Power: The Backstop That May Not Be Enough

The US offshore wind market’s survival depends heavily on state-level policy, which is independent of federal administration direction. New York, Massachusetts, New Jersey, Connecticut, and Maryland have statutory offshore wind targets — backed by state renewable portfolio standards and long-term offtake mechanisms — that are not directly affected by federal permitting changes, except insofar as the projects physically require federal (OCS) permits to build in federal waters.

New York’s Climate Leadership and Community Protection Act mandates 9 GW of offshore wind by 2035; Massachusetts has a statutory requirement for offshore wind procurement that has driven the first three award cycles from the Department of Public Utilities; New Jersey has authorised 11 GW by 2040. These state mandates are creating offtake demand — but demand that cannot be satisfied if the federal permitting pathway is blocked.

Several states are exploring legal challenges to the federal permitting pause, arguing that the executive orders exceed presidential authority over OCS leasing and permitting decisions that are governed by the Outer Continental Shelf Lands Act (OCSLA). Legal outcomes are uncertain and could take years to resolve. In the meantime, project developers are managing a portfolio of risks — permitting, financing, supply chain, and contractual — that collectively make the US offshore wind environment the most challenging among major offshore wind markets globally.

The Jones Act Constraint: A Technical Wall

The Jones Act — the 1920 Merchant Marine Act that requires vessels transporting goods between US ports to be US-built, US-flagged, and US-crewed — creates a specific and severe constraint for offshore wind installation. Wind turbine installation vessels (WTIVs) that operate in US waters installing foundations and turbines are subject to Jones Act requirements if they are transporting installation components between US ports. This effectively prohibits the use of the large European WTIV fleet — Cadeler, DEME, Jan De Nul, Heerema — that installs most offshore wind in Europe, unless they operate under a specific BOLS (Burden of Lifting Only from Sea) interpretation that limits what they can do.

The practical consequence is that US offshore wind installation requires either Jones Act-compliant vessels — of which there is effectively only one, Dominion Energy’s Charybdis, the first US-built offshore wind installation vessel, operational in 2024 — or creative operational workarounds using feeder vessels and foreign-flagged WTIVs operating in specific modes that comply with Jones Act restrictions.

Charybdis, built at Keppel AmFELS in Brownsville, Texas, is a first-of-kind vessel in the US market but is also a first-generation Jones Act-compliant WTIV in terms of capability. Its crane capacity and leg length are competitive for current turbine sizes but may be challenged by the 14–18 MW turbines that next-generation US projects are specifying. Several other US-built WTIVs are on order or in pre-contract development — Dominion has committed to a second vessel, and Crowley and others have explored Jones Act WTIV concepts — but delivery timescales push viable Jones Act installation capacity to the late 2020s at the earliest.

Developer Response: Withdrawal, Renegotiation, and Recalibration

The combination of federal policy uncertainty, cost inflation, and ITC risk has driven several major offshore wind developers to make painful commercial decisions on their US portfolios. Ørsted — the Danish developer widely regarded as the global leader in offshore wind — took impairments exceeding $4 billion on its US portfolio in 2023 and subsequently cancelled several projects including Ocean Wind 1 and 2, its New Jersey projects. The company’s US strategy has been significantly recalibrated toward a smaller, more selective portfolio.

BP and Equinor’s Empire Wind joint venture in New York has faced cost escalation and contract renegotiation. The partnership secured revised offtake agreements with the New York State Energy Research and Development Authority (NYSERDA) in 2024 at significantly higher PPA prices — reflecting the reality that original contract prices, locked in before the steel and component inflation of 2021–2023, were simply undeliverable. Other developers are in similar renegotiations across multiple states.

The developers that have maintained the most resilient US positions are those with diversified global portfolios and sufficient balance sheet strength to absorb US delays without existential consequence. Equinor, with its Slatra deepwater and NCS production cash flow, can sustain US offshore wind development through a difficult period. Smaller, US-focused developers without that balance sheet depth are at greater risk of project failure or forced asset sales.

The Long View: US Offshore Wind in 2030

Despite the current crisis, the structural case for US offshore wind — abundant resource, significant population centres within transmission distance of the East Coast shelf, state policy commitment, and the need for low-carbon electricity generation — remains intact. The 30 GW by 2030 target set by the Biden administration is clearly not achievable; an industry consensus of 15–20 GW installed by 2030 is more realistic given current permitting timelines, Jones Act vessel availability, and commercial challenges.

But 15–20 GW by 2030, rising to 50+ GW by 2040 with the right policy environment, represents a major market. The capital, the resource, the demand, and the industrial policy framework at state level all point to a long-term US offshore wind industry of genuine scale. The question of 2026 is not whether US offshore wind will ultimately succeed, but which projects survive the current storm and which developers are positioned to capture the next growth cycle when the political headwinds inevitably shift.