Key Takeaways:
- The United States has approximately 45 GW of offshore wind in various stages of development, with the bulk of near-term projects concentrated on the Atlantic Coast from Massachusetts to Virginia, but the industry has faced significant project cancellations, cost inflation, and permitting delays since 2022.
- The Jones Act — which requires vessels operating between US ports to be US-built, US-crewed, and US-flagged — creates a major constraint on offshore wind installation activity, as no Jones Act-compliant installation vessel with WTIV capability exists in the US fleet, requiring complex workarounds involving foreign-flagged installation vessels with separate US-flagged feeder vessels.
- BOEM’s (Bureau of Ocean Energy Management) offshore wind leasing programme has generated billions in competitive lease auction revenue, with areas in the Gulf of Mexico, Pacific coast, and Gulf of Maine now joining the Atlantic Coast as active leasing frontiers.
The Ambition and the Reality Gap
No offshore wind market in the world has experienced a more dramatic gap between ambition and delivery than the United States. At the time of the Biden administration’s announcement in March 2021 of a target of 30 GW of offshore wind by 2030 — a commitment greeted with enormous excitement by the industry and interpreted as a generational opportunity for wind developers, manufacturers, and supply chain businesses — the US had only about 30 MW of installed offshore wind capacity (Vineyard Wind’s Block Island Wind Farm and Dominion’s pilot at CVOW). The distance between that 30 MW reality and the 30 GW aspiration seemed bridgeable in the context of European offshore wind’s demonstrated construction rates. It has proven to be far more difficult to close than the political announcements suggested.
Between 2022 and 2024, a series of high-profile project cancellations shook confidence in the US offshore wind market. Avangrid cancelled its Commonwealth Wind project in Massachusetts; BP and Equinor wrote down their offshore wind development assets by billions of dollars; Ørsted exited its New Jersey projects and took a $4 billion impairment charge; and multiple other developers sought to renegotiate or terminate existing power purchase agreements with state utilities, arguing that cost inflation — particularly in turbines, foundations, cables, and installation vessels — had made previously negotiated prices commercially unviable. The combination of supply chain inflation (driven by post-COVID material costs and Russia-Ukraine-related energy price effects), rising interest rates that increased the cost of project financing, and the specific structural challenges of the US offshore wind market created what some in the industry described as an existential moment for the sector’s near-term ambitions.
The Jones Act: A Unique American Obstacle
The Merchant Marine Act of 1920 — universally known as the Jones Act — requires that goods transported by water between US ports be carried on vessels that are US-built, US-owned, US-flagged, and US-crewed. While the Jones Act’s primary application is to the domestic cabotage trade — bulk carriers moving grain between Gulf Coast ports and Great Lakes destinations, for example — its implications for offshore wind installation are complex and commercially significant.
Offshore wind installation activities in US waters require vessels that perform work between US ports (or between fixed offshore locations and US ports), which the Jones Act potentially covers for certain activities. The specific question of whether Wind Turbine Installation Vessels (WTIVs) — which load turbine components at US ports and install them at offshore wind farm locations — require Jones Act compliance has been the subject of regulatory guidance, waivers, and ongoing legal debate. The practical reality is that no Jones Act-compliant WTIV exists in the US fleet; building one would cost $500 million to $700 million and take 3 to 4 years. Dominion Energy has ordered a US-built WTIV (the Charybdis, built by Keppel AmFELS in Texas) specifically to address the Jones Act constraint for its Atlantic Coast projects, but this vessel represents a single asset serving one utility’s projects.
In the interim, offshore wind projects in US waters are using foreign-flagged WTIVs — primarily from European operators including Cadeler, Eneti, and Jan De Nul — operating under Jones Act workaround arrangements that involve separate Jones Act-compliant feeder barges to transport components from US ports to the installation vessel, which then installs them at the offshore wind farm location without itself transporting goods between US ports. This workaround adds cost and operational complexity compared with the integrated WTIV operation that is standard in European markets, and is one of several structural cost disadvantages that US offshore wind faces relative to its European counterpart.
BOEM Leasing and the Federal Permitting Framework
The Bureau of Ocean Energy Management (BOEM) is the US federal agency responsible for leasing offshore areas for wind energy development on the Outer Continental Shelf, with authority granted under the Energy Policy Act of 2005 and the Outer Continental Shelf Lands Act. BOEM’s offshore wind leasing programme has generated significant revenue through competitive lease auctions — the New York Bight auction in February 2022 raised over $4.37 billion from six winning bidders for leases covering approximately 480,000 acres — and has established a pipeline of leased areas on the Atlantic, Gulf of Mexico, Pacific, and Gulf of Maine coasts.
The federal permitting process for offshore wind projects — which involves BOEM’s Environmental Impact Statement review under NEPA, consultation with the US Coast Guard, NOAA Fisheries, and the US Fish and Wildlife Service, and compliance with the Endangered Species Act and Marine Mammal Protection Act — is lengthy and subject to legal challenges. Several major Atlantic Coast projects have faced litigation from fishing industry groups and, notably, from the Save the Right Whale Coalition, alleging that BOEM’s environmental reviews inadequately considered impacts on the critically endangered North Atlantic Right Whale (Eubalaena glacialis) — of which fewer than 360 individuals remain, making any additional mortality source a significant conservation concern. These legal challenges have added schedule uncertainty to projects that were already under pressure from supply chain and cost issues.
State Procurement: The Driver of US Offshore Wind Development
Unlike European markets where central government policies — UK CfD auctions, German tender rounds, Dutch SDE++ scheme — drive offshore wind development, the US offshore wind market is primarily driven by state-level renewable energy requirements. States including Massachusetts, New York, New Jersey, Virginia, Maryland, Connecticut, and Rhode Island have enacted legislation setting offshore wind procurement targets — typically expressed in gigawatts of installed capacity by a defined date — and have instructed their utilities and electricity distribution companies to conduct competitive procurement processes to contract offshore wind power.
This state-by-state approach creates both fragmentation and opportunity. Fragmentation because each state’s procurement process is separate, with different contract structures, pricing mechanisms, and requirements (some states require local content commitments, port development investments, or workforce training programmes as conditions of award). Opportunity because the cumulative commitment of the northeast US states alone represents tens of gigawatts of procurement ambition — a market of very substantial scale if it can be effectively executed. The combination of state RPS mandates, the federal Investment Tax Credit (ITC) for offshore wind, and BOEM’s federal leasing programme creates a layered incentive structure that — when it functions well — can support a viable development pipeline.
Projects Progressing: Vineyard Wind, Revolution Wind, and South Fork
Despite the industry-wide headwinds, construction has begun and is progressing on several significant US offshore wind projects. Vineyard Wind — the first commercial-scale offshore wind project in US federal waters, a 806 MW development by Avangrid and Copenhagen Infrastructure Partners (CIP) sited south of Martha’s Vineyard in Massachusetts — began turbine installation in 2024 using Siemens Gamesa 13 MW turbines on monopile foundations. Although the project has encountered delays and cost overruns that reflect the difficulties of executing a first-of-kind commercial project in a new market, its progress represents a genuine milestone for the US industry.
Revolution Wind — a 704 MW project by Ørsted and Eversource serving Rhode Island and Connecticut — and South Fork Wind — Ørsted and Eversource’s 130 MW project off New York’s Long Island, which achieved commercial operation in early 2024 as the first commercial offshore wind farm in New York state — add to the evidence that US offshore wind can be delivered. These projects, combined with Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project — at 2.6 GW, the largest planned US offshore wind project and the only one where the utility is the project developer and operator — provide real operational and construction experience that will inform the development of future projects.
The US offshore wind market of 2026 is chastened, more realistic about timelines and costs than it was in 2020 and 2021, but fundamentally still committed to building a substantial offshore wind industry. The structural demand drivers — state RPS mandates, federal climate policy, corporate renewable energy commitments from major electricity consumers, and the growing imperative to decarbonise the US power grid — remain in place. The supply chain bottlenecks, Jones Act constraints, and permitting complexities that have slowed progress are being addressed, slowly and imperfectly, through a combination of market adaptation, regulatory evolution, and the accumulation of project experience. The 30 GW by 2030 target is no longer achievable; the question now is how much capacity the industry can realistically deliver by 2030 and 2035 — and what needs to change to unlock the market’s full potential.