The UK Contract for Difference (CfD) scheme has been the engine driving Britain’s offshore wind expansion for over a decade. By providing generators with a guaranteed revenue floor — the “strike price” — CfD contracts have allowed developers to commit to offshore wind projects with long construction timelines and large capital requirements, confident that the electricity they generate will earn a predictable return regardless of volatile wholesale electricity prices. The mechanism has worked spectacularly well at driving down offshore wind costs: strike prices in early CfD rounds (AR1 in 2015) were set at approximately £120/MWh in 2012 money; by AR4 in 2022, offshore wind was clearing at approximately £37/MWh — a 70%+ reduction in the price at which offshore wind developers were willing to build. Allocation Round 5 was the exception that proved the rule — a catastrophic failure that awarded no offshore wind contracts — and AR6 has been designed to avoid repeating that outcome. Whether AR6 delivers enough capacity to keep the UK on track for its 50 GW by 2030 offshore wind target is the most consequential near-term question in UK renewable energy policy.
How CfD Auctions Work
The CfD mechanism is a reverse auction: developers bid the lowest strike price at which they are willing to build their project, and government awards contracts to the cheapest projects until the available budget (expressed in terms of annual support cost or megawatt-hour capacity) is exhausted. The strike price is the guaranteed revenue level — if the wholesale electricity market price falls below the strike price, the generator receives a top-up payment from the Low Carbon Contracts Company (LCCC); if the market price exceeds the strike price, the generator pays back the difference. This two-way payment structure means CfD contracts protect both the developer (downside price risk) and the consumer (upside price windfall).
CfD auctions are divided into technology “pots” — different technology categories that compete within their pot rather than against all technologies. Established renewable technologies (solar PV, onshore wind) compete in Pot 1; less established technologies (offshore wind, floating wind, wave energy) compete in Pot 2; and advanced (less proven) technologies compete in Pot 3. The pot structure prevents mature, low-cost technologies from winning all contracts at the expense of emerging technologies that need support to build commercial scale.
The auction process runs in rounds (Allocation Rounds 1-6 to date), with each round offering a specified volume of contracts. Developers submit bids below the published Administrative Strike Price (ASP) — the maximum price the government is willing to pay — and the auction clears at the price where supply meets demand. Multiple rounds have been run since 2015, with the government progressively adjusting the ASP, the budget envelope, and the auction rules to respond to market conditions.
AR5: The Failure Explained
Allocation Round 5, conducted in September 2023, was a high-profile failure for offshore wind procurement. The government set the ASP for offshore wind at £44/MWh in 2012 money — a figure that reflected expectations from AR4’s clearing price of approximately £37/MWh but failed to account for the rapid cost inflation that had occurred in the intervening period. Between AR4 (September 2022) and AR5 (September 2023), offshore wind project costs had increased significantly: steel prices, cable costs, installation vessel dayrates, and substation costs had all risen substantially due to supply chain inflation, higher interest rates (which increased the cost of project finance), and general construction cost inflation.
Major offshore wind developers — including Ørsted, RWE, Vattenfall, and SSE Renewables — calculated that no offshore wind project could be built profitably at the AR5 ASP of £44/MWh and declined to submit bids. The result was zero offshore wind contracts awarded in AR5 — the first time an allocation round had failed to secure any offshore wind capacity. The failure attracted enormous political attention and was widely criticised as a policy own goal that set back UK offshore wind development by at least a year.
AR6: The Recovery Round
In response to AR5’s failure, the UK government significantly revised the framework for Allocation Round 6. The ASP for offshore wind was raised to approximately £73/MWh in 2012 money — a 66% increase from AR5’s £44/MWh cap — reflecting a more realistic assessment of current project costs and allowing offshore wind developers to bid at economically viable levels. The AR6 budget was also substantially increased, targeting a significant new volume of renewable capacity contracts.
AR6 results (published in 2024) awarded offshore wind contracts to multiple projects, including fixed-bottom offshore wind farms in the North Sea and potentially early floating wind projects. The clearing prices in AR6 were substantially higher than in earlier rounds — reflecting the genuine cost increases in the supply chain — but the auction was successful in the fundamental sense of awarding contracts for significant new offshore wind capacity. The higher strike prices in AR6 will translate to higher support costs for consumers (via the Renewables Obligation / CfD levy on electricity bills), reflecting the reality that offshore wind construction costs in 2024-2026 are materially higher than in 2019-2022.
50 GW by 2030: Can It Be Achieved?
The UK government’s target of 50 GW of offshore wind by 2030 — approximately double the current installed capacity of around 14-15 GW — requires an extraordinary pace of project delivery. Even with a successful AR6 and planned AR7, the pipeline of projects that could actually be commissioned and generating by December 2030 is constrained by multiple bottlenecks: consenting timescales (major offshore wind projects currently take 4-7 years from planning submission to consent decision), grid connection queues (National Grid’s connection queue for offshore wind is measured in hundreds of projects), offshore transformer and substation manufacturing capacity, and installation vessel availability.
The government’s reformed planning system — the National Significant Infrastructure Projects (NSIP) regime administered by the Planning Inspectorate — has been accelerating, with offshore wind project decisions now targeted at two years from application submission. Grid connection reform is progressing, with National Grid ESO’s “Connections Action Plan” aiming to dramatically reduce connection waiting times. New cable manufacturing capacity is being built at facilities including Prysmian’s Gron Mård plant in Sweden and new JDR Cable Systems capacity in the UK.
Achieving 50 GW by 2030 from a standing start of ~15 GW requires adding approximately 35 GW in four years — approximately 9 GW per year of new offshore wind commissioning. For reference, the UK’s best previous year for offshore wind commissioning was approximately 3 GW. The 50 GW target is almost certainly unachievable from scratch projects alone and likely requires a combination of new build and flexible definition of what “counts” toward the target. The practical target — 40-45 GW by 2030, with 50 GW achievable by 2032-2033 — is more realistic given the supply chain and consenting constraints that the industry faces.