Key Takeaways:

  • TotalEnergies has signalled conditional resumption of on-site activity at the Mozambique LNG project as security conditions in Cabo Delgado province show tentative improvement, though an FID restart remains contingent on sustained security guarantees and political resolution of the conflict.
  • Tanzania’s offshore gas development — centred on the giant Rovuma Basin blocks operated by Equinor and Shell alongside TPDC — offers an alternative East African LNG pathway but faces its own governance and financing challenges as project timelines extend.
  • East African LNG’s window of commercial viability is narrowing as the global supply surplus from Qatar and the US closes the premium that frontier production costs need to be covered, making the case for project restart increasingly difficult to underwrite at current LNG price forecasts.
  • Mozambique LNG: Four Years of Force Majeure

    TotalEnergies declared force majeure on its Mozambique LNG project in April 2021 following a devastating attack by Islamist insurgents on the town of Palma, Cabo Delgado province, killing dozens of civilians and forcing the evacuation of project personnel. The project — which would have been the largest private investment in Africa at the time, with a project cost exceeding $20 billion — was at approximately 18–20% construction completion when work halted. The physical infrastructure — initial civil works, jetty construction, some early module fabrication — remains on site, increasingly weathered by four years of inactivity.

    The insurgency in Cabo Delgado, linked to the broader ISIS-affiliated Ansar al-Sunna Wa al-Jama’ah (locally known as Al-Shabaab) movement, has presented a sustained security challenge that the Mozambican government has been unable to resolve alone. Rwandan and SADC military deployments have stabilised parts of the province and retaken the town of Mocímboa da Praia, but the security situation in the specific areas relevant to the LNG project remains fragile. Pockets of insurgent activity, complex humanitarian dynamics, and the underlying economic and social grievances that fuel recruitment continue to make a simple “security solved” declaration premature.

    TotalEnergies’ conditional engagement signals are being read carefully by the project’s partners — Mitsui, ONGC Videsh, ENH (the Mozambican NOC), and the LNG offtakers who have long-term supply agreements underpinning the project financing. The lenders — a syndicate including the US EXIM Bank, JBIC, Standard Chartered, Société Générale, and others — have been managing the force majeure period with quarterly reviews of the security situation. Debt service obligations have been met through existing cash reserves and the project’s financial structure, but the carrying cost of a stalled project is substantial.

    The Commercial Case for Restart: Does It Still Work?

    Mozambique LNG’s commercial structure was designed around a world of tighter LNG supply and higher long-term prices than the current market environment projects. The project’s long-term LNG sale and purchase agreements (SPAs) — covering most of the first and second train output, targeting 13.1 mtpa — are oil-indexed contracts negotiated in 2017–2019, when LNG market conditions and price expectations were materially different. At Brent in the $80s and an oil slope of 12–14%, delivered LNG prices under these contracts are in the $12–$15/MMBtu range — competitive with current spot, but barely above the all-in cost of production from a delayed, cost-inflated Mozambique project.

    The original project cost estimate, before the force majeure, was approximately $20 billion for two trains. Four years of delay, with escalation in steel, equipment, labour, and insurance costs, plus the cost of demobilisation and eventual remobilisation, means the effective project cost for a restart scenario is meaningfully higher. Industry analysts have suggested a fully revised project cost in the $22–$25 billion range for a restart, though TotalEnergies has not published updated estimates. A higher capex base means a higher breakeven LNG price needed to achieve the project’s required IRR — and that breakeven is moving in the wrong direction relative to market price expectations.

    The political dimension adds another layer of complexity. Mozambique underwent a deeply contested election in October 2024, with widespread allegations of fraud and significant post-election unrest. The government’s legitimacy in the eyes of significant portions of its population is questionable, complicating international investors’ governance risk assessment. World Bank and IMF support — critical for Mozambique’s overall economic stability — has been calibrated against political reform benchmarks that the government has met only partially.

    Tanzania: The Alternative Pathway

    While Mozambique’s LNG project has been in limbo, attention has periodically turned to Tanzania as an alternative East African LNG development pathway. Tanzania holds substantial proven gas reserves — estimated at approximately 57 trillion cubic feet — in the offshore Rovuma Basin, with major discovery blocks operated by Equinor (Block 2) and Shell/Ophir heritage assets. The Tanzania Petroleum Development Corporation (TPDC) is the national NOC partner across these blocks.

    Tanzania LNG — the onshore liquefaction project proposed to take gas from offshore via subsea pipeline and export it via LNG carriers — has been in development discussions for over a decade. An Intergovernmental Agreement between Tanzania and the project sponsors was signed, host government agreement negotiations have gone through multiple rounds, and fiscal terms have been debated extensively. Yet Tanzania LNG has not reached FID, and the window for doing so in a commercially viable timeframe is narrowing as the global LNG supply surplus builds.

    The fundamental challenge in Tanzania is the fiscal and governance framework. The government’s resource nationalism instincts — understandable for a country seeking to capture maximum benefit from a transformational natural resource — have sometimes pushed fiscal terms beyond what international project finance lenders can underwrite. Natural gas pricing for domestic supply, local content requirements, and the pace and conditions of cost recovery from production are the principal sticking points. Without a bankable host government agreement, commercial lenders cannot commit, and without commercial lending, the project cannot close its financing.

    Gas-to-Power: The More Realistic Near-Term Option

    Both Mozambique and Tanzania are increasingly focusing on gas-to-power as a near-term alternative to full LNG export development. Domestic gas supply to power generation is lower-capital than LNG export, can be developed in shorter timescales, and addresses genuine development priorities — power access rates in East Africa remain among the lowest in the world. Electrification of rural and urban consumers, reduced reliance on hydro power (vulnerable to drought cycles), and industrial energy for mineral processing are all genuine value propositions for gas-to-power.

    In Mozambique, ENH and the government have advanced plans for domestic gas supply from the existing production — notably from Eni’s Coral South FLNG project, which came online in 2022 and delivers LNG to BP’s global portfolio, and from the onshore Temane field. The Coral Sul FLNG — the first FLNG vessel in Africa — has performed well technically, demonstrating that gas production from deep-water Rovuma Basin fields can be monetised reliably even amid broader project uncertainty.

    Tanzania has smaller-scale gas-to-power projects operational onshore, drawing from existing onshore fields. Expanding gas production from the offshore Mnazi Bay and Songo Songo fields to supply additional power generation capacity is a lower-risk step than LNG export development and can be implemented within the existing fiscal and regulatory framework. The International Finance Corporation and African Development Bank have both supported gas-to-power projects in the region — a signal that development finance institutions see this as the more bankable near-term pathway.

    The Regional Geopolitics: China, the West, and Energy Competition

    East Africa’s energy development landscape is increasingly shaped by competition between Chinese and Western-led investment. Chinese financing and contractors — through China EXIM Bank, CNPC’s activities in Tanzania, and infrastructure investment under the Belt and Road framework — offer a different capital and governance model than the Western-led project finance structures that IOCs and their lenders typically use. Chinese financing may be less demanding on ESG standards, governance reform, and fiscal term transparency — which can make it more attractive to governments in the short term, but may carry different long-term risks for national development outcomes.

    The US and EU are increasingly aware of this dynamic and are deploying the Development Finance Corporation (DFC), the EU’s Global Gateway initiative, and bilateral energy partnerships to offer competitive alternatives to Chinese financing for African energy projects. Whether these Western alternatives can be deployed quickly enough and on competitive terms to influence Tanzania’s and Mozambique’s project development decisions is one of the defining questions for East African energy development in the 2026–2030 period.