Key Takeaways:

  • Saipem has completed the most difficult phase of its financial restructuring — a €2 billion capital raise supported by ENI and CDP Equity — and is rebuilding its offshore construction and drilling backlog with improved contract selectivity and margin discipline, targeting EBITDA margins of 8–10% by 2026 versus near-zero at the trough.
  • The company’s structural dependency on ENI contracts — which have historically represented 25–35% of revenue — is both a commercial anchor and a strategic vulnerability, constraining Saipem’s ability to compete aggressively for non-ENI work without damaging its primary client relationship.
  • Saipem’s push into offshore wind installation — leveraging its pipelay and heavy-lift vessel fleet — is the most significant strategic diversification move, with foundations installation, cable lay, and integrated EPCI contracts for European and Middle Eastern offshore wind projects now forming a growing share of new order intake.

From Crisis to Cautious Recovery

Saipem’s near-death experience in 2021–2022 is now the industry’s most-studied case study in what happens when a major offshore contractor takes on too much fixed-price risk in a low-margin competitive environment. The combination of cost overruns on legacy EPCI contracts, the COVID disruption to offshore project execution, and the collapse of drilling activity left Saipem with a balance sheet that required emergency intervention. ENI and CDP Equity’s participation in the €2 billion capital raise in early 2022 was the financial lifeline that kept the company independent — but it came with shareholder dilution and board-level scrutiny that fundamentally changed Saipem’s governance and commercial approach.

The management team installed post-crisis — led by CEO Alessandro Puliti, himself a former ENI executive — has executed a disciplined backlog rebuild focused on selective bidding, improved risk pricing, and contract structures that share project risk more equitably with clients. The company’s order intake in 2024–2025 has been strong, with major awards in the Middle East (ADNOC’s offshore pipeline projects), West Africa (Angola deepwater SURF work), and the Mediterranean (ENI’s Coral North FLNG — the second Mozambique LNG vessel), alongside emerging offshore wind foundations and cable-lay contracts.

The financial improvement is visible in the numbers. Saipem’s adjusted EBITDA margin, which was effectively zero or negative in 2021–2022, has recovered to the 5–7% range in 2024–2025 and is tracking toward the company’s 8–10% medium-term target. Revenue has grown as the backlog converts — Saipem’s backlog exceeded €12 billion by early 2026, providing 2–3 years of revenue visibility and the operational scale needed to cover fixed costs efficiently.

The ENI Relationship: Anchor and Constraint

Saipem’s relationship with ENI is one of the most complex in the oilfield services sector — a mixture of commercial dependency, shared Italian industrial heritage, and a governance interlock that has historical roots in the post-war Italian state enterprise system. ENI is Saipem’s largest single client, founding shareholder, and strategic partner; it is also the company that forced the 2022 rescue and holds board influence that gives it input into Saipem’s strategic direction.

The commercial reality of ENI dependency cuts both ways. ENI awards Saipem significant contract volumes — often on terms that prioritise relationship over pure price competition — providing a revenue floor that independent contractors without such anchors cannot rely on. But this dependency also constrains Saipem’s competitive freedom: being seen to aggressively undercut competitors on ENI-adjacent work, or taking positions that disadvantage ENI commercially, is not a strategy Saipem’s management can pursue with full freedom.

The diversification away from ENI dependency is a stated strategic priority. Non-ENI revenue as a share of total has grown from under 60% in the peak ENI-dependency years to above 70% in the current backlog — meaningful progress but still with significant ENI concentration. Further diversification requires winning work in markets where Saipem has historically been less active: US Gulf of Mexico (where the incumbent contractors have strong relationships), Australia (where the local content environment favours established in-country players), and North Sea deepwater (where Subsea7 and TechnipFMC have entrenched positions).

Offshore Wind: The Strategic Bet

Saipem’s entry into offshore wind installation is the most strategically consequential diversification move in the company’s recent history. The company has won foundation installation contracts for several European offshore wind projects — using its heavy-lift crane vessels (the Saipem 7000, a 14,000-tonne twin-crane semi-submersible, and the Saipem Constellation crane ship) for monopile and jacket foundation installation — and is developing a cable-lay capability that could participate in the HVDC export cable installation market.

The strategic logic is compelling: the same vessels and project management capabilities that install subsea pipelines and offshore structures in oil and gas projects can, with some adaptation, be deployed for offshore wind foundation and cable installation. Saipem’s vessel fleet — particularly the heavy-lift and pipelay vessels — has specifications that are directly relevant to offshore wind work, and the company’s Mediterranean, West African, and Middle Eastern operating experience positions it for offshore wind markets in those regions that are less served by the established Scandinavian and Dutch offshore wind contractors.

The execution risk in offshore wind is real. Saipem is entering a market where DEME, Jan De Nul, Heerema, and Boskalis have decades of established relationships with wind developers and a track record of large-scale project delivery. Saipem needs to demonstrate wind-specific project execution capability before clients will award it large integrated offshore wind EPCI scopes — and the first few wind projects it executes will be closely scrutinised. The company’s Mediterranean and Middle Eastern offshore wind targets — where its regional relationships and logistics network provide genuine advantage — are the right starting point.