- Prysmian, Nexans and NKT collectively hold orderbooks full into 2029 for offshore wind cable manufacturing, with capacity expansions in progress but lead times for new orders stretching 3-4 years.
- HVDC cable demand is the tightest segment — a limited number of factories globally can produce extruded HVDC submarine cable at the voltages required for large offshore wind projects.
- Installation vessel capacity is the secondary constraint, with specialised cable-lay vessels booked years in advance for major projects.
The Offshore Wind Cable Market
Offshore wind cables fall into two main categories. Inter-array cables connect turbines within a wind farm to collector substations; these are typically HVAC at 33-66 kV and are a relatively high-volume product with multiple manufacturers. Export cables connect collector substations to shore; these range from HVAC at 132-220 kV for shorter distances to HVDC at 320-525 kV for longer distances, and are manufactured by a much smaller set of specialist producers.
The total offshore wind cable market has grown with the project pipeline. Annual delivery volumes across inter-array and export categories are in the thousands of kilometres, with export HVDC cable being the highest-value and most constrained segment. The commercial dynamics of the three main HVDC cable manufacturers — Prysmian, Nexans, and NKT — shape the global offshore wind industry’s ability to execute on its project pipeline.
Prysmian: The Scale Leader
Prysmian operates one of the largest offshore cable manufacturing networks globally, with factories in multiple European locations and acquisitions that have consolidated the industry. The company has orderbook visibility in the multi-billion euro range extending into 2028-2029, with major projects for US, UK, and continental European customers.
Prysmian has announced substantial factory capacity expansion through the current cycle. A new factory in the US to support domestic offshore wind demand was announced but the commercial plans have been affected by the pipeline contraction. European factory expansion has been more robust, with capacity additions underway in Italy, France, and elsewhere.
The company’s cable installation vessel fleet, operated through the Prysmian Powerlink subsidiary, provides integrated manufacture-and-install capability that is commercially attractive to developers seeking single-source delivery. The integration creates both commercial efficiency and execution risk concentration.
Nexans and NKT: The European Competition
Nexans, with its Halden factory in Norway as the flagship offshore cable manufacturing facility, has been a major supplier for UK and European projects. The company has been investing in capacity expansion with the Charleroi site and other European facilities. Nexans Aurora, the company’s cable-lay vessel, is a premium asset for offshore installation and has been fully booked for extended periods.
NKT operates factory capacity in Karlskrona, Sweden and Cologne, Germany for offshore submarine cable manufacturing. The company has been investing in capacity growth through the Karlskrona expansion. NKT Victoria, the installation vessel, has similar commercial characteristics to the Nexans and Prysmian installation capability.
The competitive dynamic among the three European HVDC cable suppliers has been cooperative rather than aggressive. Project awards have tended to be distributed across the three suppliers rather than concentrated, reflecting both supply chain risk management preferences of developers and the capacity constraints of any single supplier. Pricing power has been strong across all three suppliers.
HVDC: The Critical Bottleneck
HVDC submarine cable manufacturing is the tightest point in the offshore wind supply chain. Only a handful of factories globally are qualified to produce extruded HVDC cable at the voltages required for multi-gigawatt offshore wind projects (320-525 kV range). The manufacturing process requires specialised extrusion equipment, continuous vulcanisation curing, and length management that is technically demanding and capital-intensive.
The HVDC cable order-to-delivery lead time is currently 36-48 months for new orders. Projects sanctioning in 2026-2027 have effectively committed cable supply through 2030 and beyond. Developer procurement strategy has shifted to early cable ordering, sometimes pre-FID, to secure manufacturing slots.
Factory capacity expansion is underway across all three European manufacturers, but the pace of capacity growth is limited by the specialised equipment availability and the capital investment required. The commercial result is sustained pricing power for HVDC cable manufacturers and structural supply constraint on the pace of offshore wind HVDC deployment.
Inter-Array Cable Market
Inter-array cable supply is less tight than HVDC export cables. More manufacturers are qualified (including the three major HVDC suppliers plus smaller specialists), and the technical demands are less severe. Pricing pressure on inter-array cables has been more competitive, with projects able to negotiate better commercial terms than on export cables.
Standardisation on 66 kV inter-array cables has largely occurred for larger turbines, moving away from 33 kV standard used on earlier projects. The higher voltage allows fewer strings of turbines per array cable circuit, reducing total cable length and improving electrical efficiency. The transition has largely been absorbed by the supplier market without major disruption.
Installation Vessel Constraint
Offshore cable installation requires specialised vessels with large cable turntables, precise dynamic positioning, and specific cable handling equipment. The global fleet of capable vessels — Prysmian’s Leonardo da Vinci and Ulisse, Nexans Aurora, NKT Victoria, Subsea7‘s Seven Vega and Seven Arctic, and others — is booked years in advance for major projects.
New vessels have been ordered by multiple operators to expand fleet capacity. The Jan De Nul Fleeming Jenkin, and others are adding capability. But delivery lead times for cable-lay vessels are multiple years, and the gap between demand and supply has been substantial.
Developer procurement strategy increasingly combines cable manufacturing and installation in integrated contracts. Where a single cable supplier provides both manufacture and installation, commercial efficiency is better and execution risk is contained. The three major HVDC cable suppliers all offer this integrated model.
Outlook
Offshore wind cable markets through 2029 remain structurally tight. European cable factory expansion and new vessel construction will gradually ease constraints, but the pipeline of committed projects is large enough that tightness persists through the decade. Developers are increasingly securing cable supply early in the project cycle, with pre-FID procurement becoming standard practice.
For cable manufacturers, the commercial environment is the strongest it has ever been. Margins have expanded with pricing power. Capital returns to shareholders have been substantial. Capacity expansion investment is underway but measured — none of the three main suppliers wants to over-invest and face excess capacity when the cycle eventually moderates.
For offshore wind developers, cable supply is a binding constraint on project execution. Schedule planning must account for cable delivery timelines. Commercial terms have shifted to favour cable suppliers. The constraint is real, but it is known and planned around. Through the late 2020s, expect continued strong cable supplier earnings, gradual supply easing, and sustained strategic importance of cable supply chain management for offshore wind developers.