Key Takeaways:
- The submarine cable industry — dominated by Prysmian, Nexans, and NKT — is running at full capacity through 2028–2029, with lead times for HVDC export cables extending to 4–5 years, creating a critical bottleneck that is now one of the primary constraints on offshore wind project delivery in Europe and the United States.
- The root cause is structural: cable factory capacity built for the oil and gas and telecoms sectors is insufficient for the scale of power cable demand created by offshore wind, interconnectors, and the offshore grid buildout — and new factory construction takes 3–5 years from decision to production.
- Developers who secured early cable contracts for their projects are in a structurally advantaged competitive position; those who did not are facing schedule delays of 12–24 months or project cost increases from premium pricing in a constrained supply environment.
The Cable That Every Offshore Wind Project Needs — and Cannot Get Quickly Enough
An offshore wind project consists of turbines, foundations, an offshore substation, and an export cable. Of these, the turbine and foundation markets are constrained but have multiple suppliers. The export cable market has essentially three major HVDC submarine cable manufacturers in Europe: Prysmian (Italy), Nexans (France), and NKT (Denmark/Germany). For very large projects or those in deep water requiring high-voltage direct current (HVDC) technology, this effectively means a choice among three factories — all of which are currently fully booked.
The physical reason for the constraint is the specialised nature of HVDC cable manufacturing. An HVDC submarine cable for a large offshore wind farm — capable of transmitting 320 kV to 525 kV DC at gigawatt-scale power levels — is not a product that can be manufactured in a standard electrical cable factory. It requires specialised extrusion equipment for the cross-linked polyethylene (XLPE) or mass-impregnated (MI) insulation system, precision control of the extrusion process to maintain insulation integrity over cable lengths of 100+ km, custom armoring lines for the steel wire armour that protects the cable from mechanical damage and anchoring, and — critically — a cable tank or carousel of sufficient diameter and capacity to coil and store the completed cable before loading onto a cable-lay vessel.
These capital-intensive, purpose-built facilities cannot be expanded quickly. A new cable manufacturing facility — the scale of what Prysmian is building in its NKT and Prysmian expansion programmes — requires investment of €300–€500 million, a 3–5 year construction and commissioning timeline, and skilled manufacturing workers who take years to train to the precision standard that HVDC cable production requires. The announcement of a new factory today does not solve the 2026–2028 supply constraint; it addresses the 2029–2031 period.
The Demand Stack: Why Everyone Needs a Cable at Once
The offshore wind cable demand surge reflects the collision of multiple large procurement cycles simultaneously. European offshore wind — driven by REPowerEU targets of 300 GW by 2050 and national targets in the UK, Germany, the Netherlands, Denmark, and Belgium — creates a sustained and growing demand for HVDC export cables. Each major offshore wind farm (1–3.6 GW) requires a dedicated HVDC cable system; with 30–50 major projects under development or construction across Europe, the cable procurement requirement is massive.
Superimposed on offshore wind demand is the interconnector buildout. The European offshore grid — the proposed meshed HVDC network that would connect offshore wind farms to multiple countries simultaneously, as envisioned by ENTSO-E and projects like NordLink, NordSea Link, LionLink, and the North Sea Wind Power Hub — would require dozens of HVDC interconnector cables of 500 km+ length. Each of these interconnectors is itself a multi-year cable manufacturing project. The overlap between offshore wind export cable procurement and interconnector cable procurement in the same 5-year window is creating a demand spike that no realistic factory expansion scenario can fully satisfy.
The United States offshore wind market — despite its permitting challenges — has added further demand pressure. East Coast offshore wind projects are procuring export cables from European manufacturers, as the US cable manufacturing industry lacks the capacity for HVDC submarine cables at the scale required. This transatlantic demand is competing directly with European project developers for the same factory slots.
The Cable-Lay Vessel Constraint: A Second Bottleneck
Even if cable were available, the vessels needed to lay it are also in limited supply. HVDC cable-lay vessels — equipped with large carousels (able to carry 5,000–10,000 tonnes of cable), precision tensioners, and ROV systems for burial — are a specialised segment of the offshore vessel market dominated by a small number of operators. Prysmian (Leonardo da Vinci, Ulisse, and the new Pioneer), Nexans (Nexans Aurora, Nexans Skagerrak), NKT (NKT Victoria, NKT Ependadora), and Jan De Nul (Isaac Newton, Voltaire) are the principal players.
These vessels are committed years in advance to major projects — Dogger Bank, Hornsea Four, North Sea interconnectors — and their scheduling creates a secondary constraint that sits behind the cable supply bottleneck. A developer that successfully secures a cable contract but cannot book a cable-lay vessel for the required installation window faces the same schedule impact as one that has neither. Project planners are increasingly booking cable-lay vessel slots as early as cable contracts — a fundamental shift in how the offshore wind industry manages its critical path.
Industry Response: New Factories and Alternative Suppliers
The cable supply constraint is stimulating responses from multiple directions. Prysmian has committed to a major new cable manufacturing facility in the United States — to be built in Summerville, South Carolina — specifically to serve the US offshore wind market and avoid the Jones Act complications of importing European-manufactured cables. The facility is expected to be operational by 2025–2026 for dynamic cables and by 2028 for HVDC export cables.
Nexans is expanding its Halden (Norway) and Charleroi (Belgium) facilities, and has committed to a new state-of-the-art cable factory in Norway specifically focused on HVDC capability. NKT’s Cologne facility expansion and its new production line at Malmö are similarly targeted at the HVDC demand wave. These investments are significant — collectively representing over €2 billion in capital expenditure — but they are racing against a demand curve that is growing faster than the supply response.
Asian cable manufacturers — LS Cable & System (Korea), Sumitomo Electric, Furukawa (Japan), and Zhongtian Technology (China) — have the manufacturing scale for HVDC cables but have historically lacked the European grid code qualifications and the regulatory approval history needed for North Sea and European market entry. Several Asian manufacturers are actively pursuing European certification, and their entry into the market in 2027–2029 could provide meaningful supply relief. For now, however, the practical supply for European offshore wind export cables remains a three-company market.