- TotalEnergies has announced the formal restart of the Mozambique LNG Area 1 project, suspended since 2021 due to Cabo Delgado security conditions.
- Restart timelines target mobilisation through 2025-2026, with first LNG now expected in 2029 — a significant schedule extension from the pre-suspension plan.
- Buyer contract renegotiations have been completed, EPC contractor mobilisation is underway, and the security framework supporting the restart represents a multi-party arrangement involving Rwandan, SADC, and Mozambican forces.
The Suspension and Its Context
TotalEnergies declared force majeure on the Mozambique LNG project in April 2021 following a major Islamic State-affiliated insurgent assault on the town of Palma, where the project’s onshore construction activities were concentrated. The assault resulted in significant casualties, destruction of infrastructure, and evacuation of expatriate personnel. The force majeure effectively halted a project that had been one of the most visible LNG greenfield developments globally.
The security situation in Cabo Delgado had been deteriorating since 2017 with growing insurgent activity. Earlier security incidents had been absorbed by project contingency planning, but the scale of the Palma assault made continued operations untenable. The project had been approximately 30% complete at the point of suspension, with billions already invested in onshore facilities, marine terminals, and associated infrastructure.
The Security Framework
Multiple military interventions transformed the Cabo Delgado security picture through 2021-2024. Rwandan forces deployed in mid-2021, initially with approximately 1,000 troops and later expanded. SADC (Southern African Development Community) deployed a multinational force through SAMIM (SADC Mission in Mozambique) beginning in July 2021. The combined international forces, working with Mozambican FADM, progressively regained territorial control of Cabo Delgado.
Through 2024-2025, security conditions had improved sufficiently that TotalEnergies formally reassessed the restart option. The security framework supporting restart involves continued international force presence, Mozambican security sector development, and project-specific security arrangements. The arrangement is not without complexity or cost, and security expenditures will continue to be a material factor in project economics through the construction and early operations phases.
The insurgency has not been definitively defeated. Pockets of insurgent activity persist in remote areas of Cabo Delgado, and isolated incidents continue to occur. The security framework is designed to maintain the project’s operational security rather than to eliminate insurgency entirely. Whether the security situation remains stable through construction and operations is a fundamental project risk.
Project Scope and Restart Status
Mozambique LNG Area 1 targets approximately 13.1 MTPA of LNG export capacity from two trains, processing gas from the offshore Golfinho and Atum gas fields. The original FID was taken in 2019 with TotalEnergies as operator, partners including Mitsui, ONGC, ENH (Mozambique state), Bharat Petroleum, and others.
Restart activities through 2025-2026 include mobilisation of construction contractors back to site, reassessment of infrastructure condition after multi-year suspension, re-engagement of subcontractor and labour supply chains, and restart of offshore subsea infrastructure work. The schedule extension from original pre-suspension targets pushes first LNG to 2029 rather than the earlier 2024-2025 target.
Capex impact of the suspension and restart has been substantial. The cost to remobilise, cost escalation during the suspension period, security-related cost additions, and contingency for ongoing risk all add to the project cost base. TotalEnergies has not publicly disclosed specific updated capex figures, but the project cost has risen materially from the pre-FID estimate.
Buyer Contract Position
LNG offtake contracts from Mozambique LNG had been signed with multiple buyers including CPC (Taiwan), PTT Global LNG, Edison, Bharat Petroleum, Shell, Tohoku Electric, and others. The suspension created contractual complications for all parties, with delivery commitments and pricing terms requiring renegotiation.
TotalEnergies has indicated that buyer contract renegotiations have been completed or are substantially complete, with revised commercial terms reflecting the delayed delivery schedule. Specific pricing and commercial adjustments have not been disclosed publicly, but general market understanding is that buyers have accepted modified terms in exchange for continued participation in the project.
The buyer portfolio for Mozambique LNG is diverse across Asian and European markets, which provides the project with contractual resilience and diversifies counterparty risk. First LNG in 2029 positions the project’s output into a market where global LNG supply may be in oversupply condition, but the buyer contract portfolio largely protects project revenue from spot market weakness.
Contractor Re-mobilisation
The principal EPC contractor for onshore Mozambique LNG is a joint venture led by Saipem, McDermott and Chiyoda. The contractor consortium has been re-engaging with the project through 2024-2025, assessing workforce requirements, subcontractor availability, and facility condition for restart. Materials on site, facilities preserved during suspension, and logistics chain readiness are all being reviewed.
Skilled workforce availability is a specific challenge. Construction workers who had been on the Mozambique project before suspension have largely dispersed to other projects globally. Re-sourcing workforce with LNG construction experience at the scale needed for Mozambique requires extensive international recruitment, visa and security clearance processes, and training investment.
Subcontractor re-engagement involves multiple tiers of supply. Piping, electrical, instrumentation, civil, and specialty scopes all have unique challenges in re-mobilisation. Some subcontractors used on the original project have since gone out of business or changed ownership; others have been fully committed to other projects. The subcontractor landscape is different enough from 2021 that some scope may need to be re-awarded.
Area 4 and Coral LNG
Mozambique LNG Area 4, operated by Eni with partners ExxonMobil, CNPC, ENH, Kogas, and Galp, has proceeded on a different commercial path with the Coral South FLNG project delivering first LNG in 2022 and operating through the suspension period. Coral South has been the commercial success story of Mozambique LNG to date, and Area 4 is developing additional FLNG capacity through Coral North to expand output.
The Area 4 experience demonstrates that commercial LNG development in Mozambique has been feasible despite the security challenges in Cabo Delgado. FLNG deployment, with less onshore infrastructure than Area 1’s conventional liquefaction, has provided a commercial model that is less exposed to onshore security disruption. Coral North FLNG is in execution with first gas expected in 2028.
Strategic Implications
For Mozambique, the Area 1 restart and continued Area 4 development represent a critical economic opportunity. LNG revenues from the combined projects will be substantial once full production is achieved, with potential to transform the country’s fiscal position. The political and security framework supporting continued project execution is correspondingly critical.
For TotalEnergies, the restart is a commercial recovery of a major project investment. The company’s persistence through the suspension and its commitment to the restart reflects the long-term value of the asset. Successful restart and operation would validate the commercial case for investing in frontier LNG projects despite significant country risk.
For the global LNG market, Mozambique LNG adds supply into the late-2020s market that is expected to be over-supplied from other sources. The incremental volumes are modest relative to Qatari and US additions but meaningful to specific Asian and European buyer portfolios. Mozambique’s return to the LNG supply picture completes a commercial recovery story that has taken years to play out, and demonstrates the resilience of large-scale LNG projects through extreme disruption.