Offshore oil and gas production platform at sea with cranes and processing modulesOffshore oil and gas platform at sea
  • The Stabroek Block has transformed Guyana into a top-ten global oil producer in under a decade, with a multi-FPSO development strategy that is unprecedented in pace and scale for a frontier basin.
  • ExxonMobil, Hess, and CNOOC are executing a five-FPSO development programme targeting over 1.2 million bopd by the late 2020s, making Guyana one of the most capital-efficient deepwater provinces ever developed.
  • The resource base — now exceeding 11 billion barrels of oil equivalent — continues to grow with each exploration campaign, raising serious questions about how quickly the country and its partners can monetise stranded volumes before the energy transition reshapes the demand landscape.

From Frontier Curiosity to Global Powerhouse

A decade ago, Guyana wasn’t on most oil executives’ radar. The country had a modest onshore petroleum history and virtually no offshore infrastructure to speak of. Fast forward to mid-2026, and Guyana has become one of the most-discussed deepwater provinces on the planet — producing approaching 700,000 barrels of oil per day and with a development programme that makes even the most ambitious North Sea or Gulf of Mexico projects look cautious by comparison.

The catalyst was the Liza-1 discovery in 2015 — ExxonMobil’s drillship Deepwater Champion punching into the Cretaceous-aged Liza reservoir and encountering over 300 feet of net oil pay. That well changed everything. What followed was one of the most aggressive appraisal and development programmes in industry history, with ExxonMobil, its partners Hess Corporation and CNOOC, and the Guyanese government moving at a pace that surprised even veteran observers.

What makes Guyana remarkable isn’t just the volume of hydrocarbons discovered — the estimate now sits above 11 billion barrels of oil equivalent across the Stabroek Block — it’s the fiscal terms, the reservoir quality, and the sheer efficiency of the development execution. The block’s Cretaceous turbidite sandstones are well-sorted, highly porous, and laterally continuous. These aren’t the complicated chalk reservoirs of the North Sea or the fractured basement plays of Southeast Asia. They’re geologically predictable, which translates to consistent well performance and high recovery factors.

The FPSO Development Strategy: Five Hulls, One Vision

The Stabroek Block development is built around a sequential FPSO deployment strategy that has no real parallel in offshore history in terms of speed. The first vessel, Liza Destiny, a converted VLCC with 120,000 bopd nameplate capacity, achieved first oil in December 2019 — just four years after discovery. That’s a development timeline that would make most North Sea operators choke on their coffee.

The second unit, Liza Unity, entered service in early 2022, adding another 220,000 bopd of production capacity. Then came Prosperity for the Payara development, with 220,000 bopd capacity, sanctioned at a project cost of around $9 billion. As of mid-2026, Prosperity is producing at or near design rates, and the Hammerhead FPSO — the fourth unit — is in the advanced stages of construction and hook-up preparation. A fifth FPSO, for the Whiptail development, has been sanctioned with SBM Offshore contracted for the hull conversion and topsides integration.

Each successive FPSO has been larger and more technically capable than its predecessor. The Hammerhead unit will have capacity of 250,000 bopd and is designed around lessons learned from the earlier three. Water injection capacity has been increased significantly, reflecting the reservoir management insights gained from the Liza Phase 1 and Phase 2 operations. Gas handling has also been improved — Guyana’s gas balance is a critical consideration given the associated gas volumes produced alongside oil.

The technical specification work on these FPSOs has been extensive. Mooring systems in the Stabroek operating environment — water depths ranging from around 1,500 to 2,200 metres — require spread mooring or turret designs that can handle Atlantic swell conditions and seasonal current variations. The Liza Destiny uses a disconnectable turret mooring system, which was partly dictated by hurricane risk assessments, though Guyana sits south of the main hurricane belt and the actual weather window risk is considerably lower than, say, the Gulf of Mexico.

Production Ramp: Numbers That Command Attention

Guyana’s production trajectory is genuinely jaw-dropping when placed in context. In 2020, the country produced around 75,000 bopd. By 2023, it had crossed 400,000 bopd. By mid-2026, production is approaching 700,000 bopd across the three producing FPSOs, making Guyana a larger producer than several long-established OPEC members. The development partners’ target — stated publicly — is production exceeding 1.2 million bopd by 2027-2028 with all five FPSOs operational.

For context, that would put Guyana roughly on par with Kazakhstan and significantly ahead of the UK’s entire offshore production base. From zero to one million barrels per day in about twelve years, all from a single deepwater block. It’s one of the most remarkable development stories in the industry’s history.

The economics underpin everything. Guyana’s Production Sharing Agreement (PSA) with the Guyanese government and the state oil company, Guyana Energy (formerly NGAS, and before that the Guyana government’s interest was held through Guyana’s Natural Resources Fund), is structured to deliver substantial government take as costs are recovered. The cost recovery mechanism has attracted significant scrutiny domestically, with critics arguing that the PSA terms are too generous to ExxonMobil. The government and Guyana Energy have consistently pushed back on these characterisations, pointing to the billions of dollars flowing into the Natural Resources Fund.

What’s not in dispute is the breakeven economics. The deepwater Stabroek barrels break even at a Brent oil price well below $35 per barrel on an operating cost basis, making them competitive with any major deepwater province globally and comfortably below the North Sea average. At current Brent prices in the $70-80 range, the project generates substantial free cash flow for all three partners.

Reservoir Management: The Long Game

Running a multi-FPSO deepwater operation at this scale requires sophisticated reservoir management, and ExxonMobil has been deploying its full technical toolkit here. Water injection is central to the strategy — the Liza reservoirs are pressure-depleting without strong natural aquifer support, and maintaining reservoir pressure through water injection is essential for achieving target recovery factors.

The injection water infrastructure across the block is significant. Each FPSO has seawater treatment and injection capacity sized to maintain voidage replacement ratios appropriate for each reservoir. The subsea infrastructure connecting injector wells to the FPSO manifolds involves substantial umbilical and flowline scopes — TechnipFMC has been heavily involved in the SURF work across multiple phases, alongside McDermott for installation.

Gas management is the other major technical challenge. The Stabroek reservoirs produce significant associated gas, and the development concept is premised on gas reinjection for pressure maintenance, with surplus gas used for fuel and power generation on the FPSOs. The long-term plan involves monetising gas through LNG exports or domestic power generation, but the infrastructure for that doesn’t yet exist at scale. Gas reinjection is therefore the near-term reality, which adds complexity to the FPSO topsides design and the subsea compression systems.

The Hess Acquisition Complication

No discussion of Guyana in 2026 is complete without addressing the Chevron-Hess acquisition saga, which has been the industry’s most protracted M&A drama of the decade. Chevron announced its $53 billion acquisition of Hess Corporation in October 2023, with Hess’s 30% working interest in the Stabroek Block being the prize asset — arguably the most valuable non-operator position in the deepwater world.

What followed was an eighteen-month legal battle, centred on whether ExxonMobil and CNOOC had pre-emption rights over Hess’s Stabroek stake under the terms of the joint operating agreement. ExxonMobil and CNOOC both claimed pre-emption, arguing that Hess’s sale to Chevron triggered their right of first refusal. This dispute went to arbitration, with the industry watching closely given the enormous stakes — Hess’s Guyana stake alone was valued by analysts at over $30 billion at Brent prices of $75.

The arbitration concluded in mid-2025 with the arbitrators finding in favour of Chevron, ruling that the pre-emption rights were not triggered by the transaction structure. Chevron’s acquisition of Hess completed shortly thereafter, making Chevron the new 30% partner in Stabroek alongside ExxonMobil’s 45% and CNOOC’s 25%. The resolution cleared a significant overhang for the development programme, which had continued operating throughout the dispute period but with uncertainty about the future governance structure.

Exploration Upside: The Resource Keeps Growing

What distinguishes the Stabroek Block from most mature deepwater provinces is that the exploration story is far from over. ExxonMobil and its partners have made over thirty significant discoveries on the block since 2015, and the exploration drilling programme continues to add resources at a pace that comfortably outstrips the development programme’s ability to monetise them.

The most recent exploration wells have tested the deeper Paleocene and Campanian plays on the block, which add a new geological dimension to the resource base. The Cretaceous turbidites that host the main Liza, Payara, and Whiptail accumulations are well understood. The deeper plays are higher-risk but potentially very large.

Beyond Stabroek, the broader Guyana-Suriname Basin is attracting increasing attention from other operators. TotalEnergies and APA Corporation are advancing the Sapakara and Kwaskwasi discoveries in Suriname’s Block 58, which is directly analogous to the Stabroek play fairway. The geological continuity across the maritime boundary between Guyana and Suriname suggests that the basin-wide resource base could ultimately exceed 15-20 billion barrels of recoverable oil equivalent.

Infrastructure and Local Content: The Guyanese Dimension

The rapid pace of development has put enormous strain on Guyana’s onshore and offshore support infrastructure. Georgetown, the capital, is experiencing infrastructure development challenges that are directly linked to the oil boom — everything from housing costs to port capacity is under pressure. The Demerara Harbour area has seen substantial investment in offshore logistics, vessel laydown, and fabrication facilities.

Local content has been a consistent point of tension between the operators and the Guyanese government. The PSA includes local content obligations, and the government has pushed aggressively to ensure that Guyanese companies and workers participate meaningfully in the supply chain. In practice, this is challenging — the technical requirements of deepwater FPSO operations don’t align easily with the skills and capabilities available in a small developing nation. ExxonMobil has invested in training programmes, and a domestic workforce is gradually developing, but the gap between government expectations and operational reality remains significant.

The shipping logistics are also noteworthy. Guyana’s crude — Liza Light, with an API gravity in the low 30s and very low sulphur content — is being loaded onto VLCCs for export to refineries in the US Gulf Coast, Europe, and Asia. The country’s lack of deep-water berthing infrastructure means that crude is loaded offshore via ship-to-ship transfer or at single point mooring systems associated with each FPSO. As production approaches one million bopd, the export logistics infrastructure will need significant expansion.

Energy Transition Tension: How Long Does the Window Stay Open?

The elephant in every Guyana boardroom is the energy transition. Guyana is ramping up oil production at precisely the moment when the long-term trajectory of global oil demand is increasingly uncertain. ExxonMobil has been characteristically robust in its position — Guyana’s low-breakeven barrels will be among the last to leave the global supply mix in any demand scenario — but the Guyanese government faces a more nuanced challenge.

The country’s entire economic development strategy is now tethered to oil revenues flowing into the Natural Resources Fund. The fund is intended to provide intergenerational wealth and insulate the economy from commodity price volatility — a classic sovereign wealth fund model. But the fund’s effectiveness depends on oil prices and production remaining robust for decades. If global demand peaks earlier than expected, or if Brent prices decline structurally, Guyana’s development model faces a serious stress test.

For now, the numbers are working. The Natural Resources Fund had accumulated over $2 billion by early 2025 and continues to grow. The government is investing in education, healthcare, and infrastructure. The challenge — familiar from Norway, the UAE, and other resource-rich nations — is converting finite hydrocarbon wealth into durable economic development. Guyana is still early in that transition, and the Stabroek Block’s extraordinary production ramp is both its greatest asset and its most significant source of long-term risk.

What Comes After the FPSO Programme?

With five FPSOs planned and a resource base that exceeds what can be developed with the current programme, the question of what comes next is live. ExxonMobil and partners have already identified further development areas on the Stabroek Block — the Hammerhead North, Lancetfish, and Cataback discoveries among them — that could support additional FPSOs beyond the current five-vessel plan.

There’s also the question of gas monetisation. Reinjection is a temporary solution. The long-term options include pipeline gas exports to the Caribbean or the US, small-scale LNG, or domestic power generation. A final investment decision on gas infrastructure has been repeatedly deferred, partly because the development priority has been oil, and partly because gas markets are challenging. But as associated gas volumes grow with each additional FPSO, the gas problem will become harder to defer.

Whatever the long-term trajectory, the Stabroek Block has already written its chapter in offshore industry history. The speed of development, the scale of the resource, and the capital efficiency achieved are genuinely exceptional. For operators, investors, and policy professionals watching the global upstream landscape, Guyana is the most important deepwater story of the decade — and it’s still very much being written.