- Floating offshore wind — placing turbines on anchored floating structures rather than fixed-bottom foundations — is the technology that unlocks deeper water sites where 80% of the world’s best offshore wind resource sits, but the gap between demonstration projects and commercial-scale economics has proven stubbornly wide.
- Three main foundation concepts — spar buoys (Equinor’s Hywind), semi-submersible platforms (Principle Power’s WindFloat, Ideol’s Damping Pool), and Tension Leg Platforms (TLPs) — each have distinct technical and commercial trade-offs, and no single concept has yet established the dominant position that the monopile achieved in fixed-bottom markets.
- The mooring and anchoring system — typically synthetic fibre or chain catenary moorings with drag embedment anchors or suction anchors — is one of the most significant cost drivers in floating wind, and advances in mooring system design are essential to closing the gap to fixed-bottom economics that the commercial scale-up of floating wind requires.
The Water Depth Barrier and Why Floating Matters
The vast majority of installed offshore wind capacity sits in water depths below 60 metres — the practical maximum for conventional monopile foundations using current installation vessel technology. This shallow-water zone hugs the coastlines of the North Sea, the Baltic, and near-shore areas of the US East Coast, the UK’s Western Approaches, and parts of Asia. Beyond 60 metres depth, the fixed-bottom economics deteriorate sharply as monopile sizes, installation complexity, and steel tonnage all increase faster than the energy output improvements from deeper, windier sites.
The floating wind opportunity is significant: water depths of 60-1,000 metres cover enormous areas of the global ocean, including the most energetic Atlantic weather systems, the deep Norwegian Sea, the US West Coast (where virtually all offshore wind potential sits in water deeper than 60 metres), Japan, South Korea, and much of the Mediterranean and tropical offshore zones. The wind resource at these deeper-water sites is often superior to what’s available in the shallow-water zones already exploited — higher wind speeds, more consistent flow, less wakes from adjacent farms.
Spar Buoys: Equinor’s Hywind Concept
Equinor’s Hywind concept — a deep-draft cylinder ballasted at the bottom with a turbine mounted at the top — was the first floating wind concept to reach commercial deployment. The Hywind Scotland project (30 MW, 5×6 MW Siemens turbines) began generating power in 2017, providing the world’s first commercial-scale demonstration that floating wind works technically. Hywind Tampen, a larger 88 MW project supplying power to Equinor’s Snorre and Gullfaks oil platforms (and reducing their gas turbine emissions), commissioned in 2023 at a scale that moved the technology clearly beyond demonstration.
The spar’s operating principle relies on deep draft — the cylinder extends 100+ metres below the waterline, putting the buoyancy centre well below the wave zone and providing inherent stability without active motion compensation. The spar concept has strong stability credentials and can be deployed in very deep water (200-700 metres), but it has significant limitations. Spars cannot be assembled in shallow-water ports — the deep draft requires they be towed to site nearly fully assembled, limiting port logistics options. And the required water depth (minimum approximately 100-150 metres for safe mooring) excludes the large intermediate-depth zone between 60 and 150 metres, which contains substantial wind resource.
Semi-Submersible Platforms: The Versatile Middle Ground
Semi-submersible floating foundations — drawing on the same hydrodynamic principles as the drilling semisub — use multiple partially submerged columns and pontoons to achieve stability through distributed buoyancy rather than deep draft. The design can be adapted for a wide range of water depths (as shallow as 50 metres in some configurations) and can be constructed and assembled in conventional shipyards or drydocks, then wet-towed to site with the turbine already assembled — a potential supply chain advantage over the spar concept.
WindFloat Atlantic (25 MW, Portugal), the Provence Grand Large project (25 MW, France), and the first commercial scale projects in the UK (Celtic Sea Round 6 licences) are primarily using semi-sub concepts. The competing semi-sub designs — Principle Power’s WindFloat, BW Ideol’s Damping Pool (barge-type with a central moonpool that damps wave-induced motion), Stiesdal Offshore’s TetraSpar (assembled from standard structural elements), and Hexicon’s dual-turbine twin-hull concept — each have distinct structural philosophies and manufacturing strategies.
Tension Leg Platforms: High Performance, High Cost
Tension Leg Platforms (TLPs) anchor the floating foundation to the seabed using vertical tensioned tendons rather than slack catenary moorings. The vertical tensioning eliminates the heave and pitch motion that moored floating structures experience, providing the most motion-stable platform geometry of the three main floating wind concepts — important for maximising turbine performance and potentially reducing drivetrain fatigue loads. The tradeoff is that TLPs require seabed conditions suitable for driven or suction pile anchors, and the tendon tension forces require careful structural engineering of both the platform and the anchor system.
TLP floating wind concepts are being developed by COWI (in collaboration with Iberdrola), PelaStar, and others, but commercial-scale deployment has not yet been achieved. The capital cost premium relative to semi-sub and spar concepts is the primary barrier — the tendon and anchor system adds significant cost, and the advantage of superior motion performance needs to translate into demonstrable economic value (through lower turbine OPEX or higher availability) to justify the capital premium in a competitive market.
The Economics Gap: From Demonstration to Commercial
The fundamental challenge for floating wind is the economics gap relative to fixed-bottom. Current floating wind projects are delivering electricity at £150-200 per MWh on a levelised basis — two to three times the LCOE of mature fixed-bottom offshore wind in equivalent wind resource areas. This gap needs to close substantially before floating wind can compete commercially without exceptional government subsidy support.
The pathways to cost reduction are the same as they were for fixed-bottom wind in the 2010s: technology standardisation (reducing the number of competing concepts to a few with scale advantages), manufacturing volume (driving down component costs through scale), installation efficiency (developing purpose-built tow-out and commissioning procedures), and supply chain development (building mooring chain, anchor, and floating structure manufacturing at scale). None of these are quick processes — the fixed-bottom wind journey from early commercial scale to current economics took approximately fifteen years. Floating wind is perhaps five to eight years into that journey.
The UK’s ScotWind leasing round — which awarded seabed rights for up to 25 GW of floating and fixed-bottom wind in Scottish waters — includes substantial floating wind commitments from developers including BP, Shell, Equinor, and TotalEnergies. These commitments, backed by real capital from companies with the financial strength to absorb early-stage floating wind economics, represent the demand signal the supply chain needs to justify scale investment. The 2030s will determine whether floating wind delivers on its potential or remains a permanent niche alongside the dominant fixed-bottom market.