- Eni, PETROCI and Vitol have committed roughly $4 billion to Baleine Phase 3, a development set to push the field’s combined output toward 150,000 barrels of oil per day and 200 million cubic feet of gas.
- Altera Infrastructure has signed EPCIC and a 15-year bareboat charter for a newbuild FPSO to be built by Wison New Energies in China, rated for 90,000 bpd of oil processing, 160 MMscfd of gas handling and 1.4 million barrels of storage.
- The project underscores a wider West African trend: fast-tracked, low-carbon-intensity deepwater developments financed through tight equity-contractor-state partnerships rather than traditional single-operator models.
A Field That Rewrote Ivory Coast’s Energy Map
Four years ago, Côte d’Ivoire was a footnote in West African upstream circles, a modest oil producer overshadowed by Nigeria, Angola and Ghana. That changed in September 2021, when Eni announced the Baleine discovery roughly 60 kilometres off Abidjan, in water depths that, unusually for a deepwater West African play, sit closer to 1,000 metres than the 2,000-plus metres typical of Angola’s pre-salt or the US Gulf of Mexico’s Lower Tertiary. Eni pitched Baleine as one of the fastest field developments in the industry’s history, and it delivered: first oil arrived in August 2023, less than two years after sanction, at a time when most deepwater projects were still measuring their pre-FID engineering studies in years, not months.
What made Baleine remarkable wasn’t just speed. It was the carbon intensity claim, near-zero routine flaring, gas reinjection instead of venting, and an FPSO-centric architecture built to minimise the topsides footprint. Eni has leaned hard into that positioning, and whatever one makes of the marketing, the reservoir engineering underneath it is genuinely unusual: a shallow-ish, high-quality carbonate and clastic sequence with associated gas that made phased development economically attractive from day one, rather than requiring the field to be produced flat-out to repay a single, monolithic capex bill.
Phase 1 and Phase 2: The Fast Track to 60,000 bopd
Phase 1 brought roughly 15,000 bopd onstream using the Petrojarl I FPSO, a conversion vessel chosen specifically because it was available quickly, not because it was purpose-built for the field. That pragmatism defined the whole Baleine philosophy: get barrels flowing, generate cash flow, and let subsequent phases fund themselves rather than front-loading all the capital risk into a single mega-project sanction.
Phase 2, which reached first production in December 2024, roughly quadrupled that rate. Eni confirmed output climbing to approximately 60,000 bopd of oil alongside 70 million cubic feet a day of associated gas, the equivalent of about 2 million cubic metres of gas reinjected or used for domestic power generation. For a country whose entire prior oil output rarely broke 40,000 bopd from legacy fields, Baleine Phase 2 alone came close to doubling national production. Ivorian officials have been unusually candid that the field’s tax and royalty terms, structured under a production-sharing contract with state player PETROCI, are now a material line item in the national budget, not a rounding error.
What Phase 3 Actually Adds
Phase 3 is the step-change. Eni and its partners are targeting total field output of around 150,000 barrels of oil equivalent per day once the new capacity is online, more than double current levels, with associated gas processing rising to roughly 200 million cubic feet a day. Reported capital commitment across the phase sits at approximately $4 billion, a figure that spans the new FPSO newbuild, subsea infrastructure, drilling of additional production and injection wells, and topside gas handling expansion.
Unlike Phase 1 and 2, which leaned on a converted vessel, Phase 3 is built around a dedicated newbuild FPSO, a signal that Eni and partners now view Baleine as a long-duration, multi-decade asset rather than an early-life pilot. That’s an important distinction for anyone reading the reserves story: newbuild FPSO commitments of this size are not made against marginal, short-plateau fields. They are made against reservoirs operators expect to still be producing in the late 2030s and beyond.
Inside the New FPSO: Wison’s Build, Altera’s Charter
The vessel itself is where this story gets technically interesting. Altera Infrastructure, the Bermuda-based FPSO and shuttle tanker specialist spun out of Teekay’s offshore business, has signed EPCIC (engineering, procurement, construction, installation and commissioning) agreements with Eni, paired with a firm 15-year bareboat charter, the standard commercial structure that lets an operator secure guaranteed floating production capacity without owning the asset outright.
Construction has been contracted to Wison New Energies, a Chinese yard that has been steadily building a track record in FPSO topsides and hull fabrication as the traditional Korean heavy-lift yards run at capacity on LNG carrier and drillship orders. The new vessel is designed for 90,000 bpd of oil processing capacity, 160 million standard cubic feet a day of gas processing, and roughly 1.4 million barrels of crude storage, specifications that put it in the upper-middle tier of the current global FPSO newbuild fleet, smaller than the giant Guyana-bound vessels delivered for ExxonMobil, but comfortably larger than most West African conversions of the last decade. Water depth at the Phase 3 location is expected to sit in the 800 to 1,200 metre range, still shallow by deepwater FPSO standards, which keeps mooring and riser engineering commercially manageable compared with ultra-deepwater developments in the Gulf of Mexico or Brazil’s Santos Basin.
The Commercial Architecture: PETROCI, Vitol, and Eni’s Equity
Baleine’s ownership structure is worth understanding because it explains why the project has moved so fast relative to peers. Eni operates the licence, but PETROCI, Côte d’Ivoire’s state hydrocarbons company, holds a meaningful working interest, giving the government direct exposure to upside rather than relying solely on royalty and tax terms. Vitol, the trading house, has also taken an equity position, an increasingly common pattern where trading majors use upstream stakes to lock in offtake and physical barrels for their global crude books rather than purely to earn exploration and production returns.
That combination, an IOC bringing technical and project-delivery capability, a trading house bringing marketing muscle and balance sheet, and a state company bringing regulatory alignment and local content credibility, has become something of a template for fast-tracked West African deepwater projects since 2020. It’s a notably different model to the classic operator-led joint venture between two or three IOCs, and it’s one worth watching as Senegal, Namibia and other frontier basins mature.
West Africa’s FPSO Market Context
Baleine Phase 3 lands into an FPSO market that is, by most contractor accounts, tighter than it has been in a decade. SBM Offshore, MODEC and BW Offshore have order books stretching years out, driven by Guyana, Brazil and now a fresh wave of West African sanctions from Senegal’s Sangomar to Namibia’s still-pending Venus development. Altera’s move to bring a newbuild through Wison, rather than competing for slots at the established Korean or Singaporean yards, reflects a broader industry response: when the traditional top-tier yards are booked solid, contractors are qualifying second-tier and emerging yards to keep newbuild schedules credible.
For operators, that yard diversification cuts both ways. It expands available capacity and, in theory, competitive tension on price, but it also introduces execution risk around quality assurance, welding and fabrication standards, and schedule discipline that established yards have spent decades derisking. Eni’s willingness to back a Wison-built hull for a flagship, newbuild-grade FPSO is itself a data point on how far Chinese fabrication capability has progressed in a sector historically dominated by Korean and Singaporean players.
Reservoir and Water Depth: The Engineering Reality
What sets Baleine apart technically is the combination of an oil rim with a large associated gas cap, sitting at water depths shallow enough to simplify mooring but deep enough to require dynamically-positioned or spread-moored FPSO infrastructure rather than fixed platforms. Riser and umbilical design has had to account for a phased tie-back strategy, new wells and manifolds added incrementally as each phase comes online, rather than a single field-wide subsea architecture designed and installed in one campaign. That incremental approach is efficient for capital phasing, but it places a premium on flow assurance planning: operators need confidence that hydrate and wax risk across old and new flowlines remains manageable as the network grows organically rather than by master design.
Local Content and Ivorian Capacity Building
Côte d’Ivoire has pushed local content requirements harder with each Baleine phase, and Eni has responded with onshore fabrication yard investment near Abidjan, expanded technical training programmes, and Ivorian staffing targets embedded in the PSC terms. It’s a familiar playbook from Ghana’s Jubilee and Nigeria’s deepwater licences, but Baleine’s compressed development timeline has forced much of that capacity building to happen concurrently with construction rather than sequentially, a genuine logistical challenge for a country with a thin pre-existing offshore oil and gas workforce.
Whether that capacity building outlives the field, whether Ivorian engineers trained on Baleine end up staffing future regional projects in Ghana, Senegal or Nigeria, will be one of the more interesting secondary storylines to track as West Africa’s deepwater province matures beyond its historical Nigeria-Angola axis.
Execution Risk and the Road to First Oil
No project of this scale is risk-free. Phase 3’s timeline depends on Wison delivering a newbuild hull and topsides on schedule from a yard still building its FPSO track record, on subsea installation vessels being available in a West African market where SURF contractors are stretched across Senegal, Nigeria and Angola simultaneously, and on drilling rigs being contracted for the additional production wells Phase 3 requires. Dayrate inflation across the West African jack-up and semisubmersible fleet over the past two years means well costs for Phase 3 will likely run meaningfully higher than the assumptions baked into Phase 1 and 2 economics.
There’s also reservoir risk that doesn’t disappear just because Phases 1 and 2 performed well. Carbonate reservoirs can behave unpredictably as offtake rates rise, and doubling field output brings genuine questions around pressure maintenance, water and gas breakthrough timing, and whether the existing well stock plus planned Phase 3 wells will sustain the targeted plateau rather than seeing an early decline.
The Bigger Picture: West Africa’s Deepwater Revival
Baleine Phase 3 is not an isolated data point. It sits alongside Senegal’s Sangomar ramp-up, Nigeria’s Bonga North sanction, and Namibia’s still-maturing Orange Basin discoveries as evidence that West Africa’s deepwater story has genuinely broadened beyond the traditional Angola-Nigeria core. For contractors, that means a multi-basin pipeline of FPSO, subsea and drilling work extending well into the 2030s. For Côte d’Ivoire specifically, it means a national economy recalibrating around oil and gas revenue at a scale nobody was modelling five years ago, and a government now facing the familiar West African challenge of turning fast hydrocarbon cash flow into durable, diversified economic development rather than a short-lived commodity windfall.
What to Watch Next
For contractors and investors tracking this story, three signposts matter most over the coming eighteen months. First, Wison’s fabrication schedule at its Chinese yard, any slippage there cascades directly into Eni’s targeted Phase 3 first-oil date and will be the clearest early indicator of whether newer FPSO yards can match Korean and Singaporean delivery reliability on a flagship contract. Second, the drilling campaign backing Phase 3, rig selection, spud dates and early well results will start to answer the reservoir performance questions that inevitably follow a plateau-doubling development. Third, watch PETROCI’s public statements on revenue allocation; Côte d’Ivoire’s government has staked considerable political capital on Baleine translating into visible infrastructure and social spending, and Phase 3’s cash flows will be the first real test of whether that promise survives contact with a national budget.
Regionally, Baleine Phase 3 also raises the stakes for competing West African deepwater capital. Every FPSO slot Wison and Altera commit to Baleine is one fewer newbuild berth available to Senegal, Namibia or a prospective second Nigerian sanction in the near term, and operators across the basin are watching yard capacity as closely as they watch crude prices. In a market where SBM Offshore, MODEC and BW Offshore are already quoting multi-year lead times, Côte d’Ivoire’s ability to secure capacity ahead of its neighbours is itself a competitive advantage that other West African governments are taking note of.